top of page

Dakota St Sidewalk & Spruce/Elm St Drainage (2023-2)

Construction Updates

*The city of Kindred will try to provide timely, relevant, and up-to-date information regarding this project as it becomes available to us. If you have any questions or would like to see additional information, please contact any city staff, council, or the project engineer. Thank you!

 

Project Schedule:

9/11/2023: Mobilize to Phase 1, Install Fire Hydrant

9/13/2023 - 9/22/2023: Phase 1 Grading

9/25/2023 - 10/6/2023: Phase 1 Sidewalk

10/05/2023 - 10/07/2023: Mobilize to Phase 1, Begin on Pipe Conduit

10/09/2023 - 10/14/2023: Complete Pipe Conduit and begin Phase 1 Grading

10/16/2023 - 10/21/2023: Complete Phase 1 Grading - begin on sidewalks

10/23/2023 - 10/28/2023: Work on Phase 1 Sidewalks

Project Documents:

2023-2 Improvement District Map

2023-2 Sidewalk & Drainage Improvement District Construction Details 6.28.2023

2023-2 Sidewalk & Drainage Improvement District Estimated Special Assessments 7.17.2023

bottom of page