Dakota St Sidewalk & Spruce/Elm St Drainage (2023-2)
Construction Updates
*The city of Kindred will try to provide timely, relevant, and up-to-date information regarding this project as it becomes available to us. If you have any questions or would like to see additional information, please contact any city staff, council, or the project engineer. Thank you!
Project Schedule:
9/11/2023: Mobilize to Phase 1, Install Fire Hydrant
9/13/2023 - 9/22/2023: Phase 1 Grading
9/25/2023 - 10/6/2023: Phase 1 Sidewalk
10/05/2023 - 10/07/2023: Mobilize to Phase 1, Begin on Pipe Conduit
10/09/2023 - 10/14/2023: Complete Pipe Conduit and begin Phase 1 Grading
10/16/2023 - 10/21/2023: Complete Phase 1 Grading - begin on sidewalks
10/23/2023 - 10/28/2023: Work on Phase 1 Sidewalks
Project Documents:
2023-2 Improvement District Map
2023-2 Sidewalk & Drainage Improvement District Construction Details 6.28.2023
2023-2 Sidewalk & Drainage Improvement District Estimated Special Assessments 7.17.2023